Batteriespeichersystem (BESS) Balzers

Liechtensteinische Kraftwerke·Schaan, Liechtenstein·Deadline Jul 03, 2026 · 12 days left·Open·Supplies
Structured notice only
50/100

Opportunity Score

Needs reviewMedium complexity
SuppliesOpen
Why this score?

Opportunity

50 / 100

Complexity

65 / 100

Risk factors

No estimated value, incomplete award criteria details, and no selection criteria explicitly listed in provided data. Bi...

Execution deadline of 12 months for a large BESS may be aggressive; delays could incur penalties.

Submission deadline in 12 days

Deep Portfolio Analysis

Deep Company Fit Analysis

Uses:

  • Description
  • Industries & Services
  • Capabilities
  • Market & Experience
  • Certifications

Overview

Moderate opportunity

Key Facts

  • Supplies contract
  • 1 lot
  • Duration 132 MONTH
  • Supply of a grid-connected battery storage system (BESS) with minimum 25 MW / 50 MWh capacity
  • Delivery to site in Balzers, FL-9496
Show full summary

Liechtensteinische Kraftwerke (LKW) issues an open tender for the supply, installation, and commissioning of a grid-connected battery energy storage system (BESS) in Balzers, Liechtenstein. Minimum capacity: 25 MW / 50 MWh. The contract includes a 12-month execution period followed by a mandatory 120-month warranty and service phase (total 132 months). Single lot; procedure is open with electronic submission required. No estimated value published. Award based on price (75%) and quality (25%, including execution time and other unspecified quality criteria). Deadline for tenders: 2026-07-14.

Risks

No estimated value, incomplete award criteria details, and no selection criteria explicitly listed in provided data. Bi...

Execution deadline of 12 months for a large BESS may be aggressive; delays could incur penalties.

Submission deadline in 12 days

Analysis may be incomplete

Only part of the procurement documentation was analyzed. Additional eligibility requirements, certificates, or submission documents may exist in the remaining tender documentation.

Key Requirements

Technical

  • Minimum capacity: 25 MW / 50 MWh
  • Grid-connected system for Balzers site
  • Execution within 12 months

Requirements may be incomplete.

Award Criteria

Lot 1

Ausführungszeit (bis zur Inbetriebnahme)0.06%

Buyer

Name

Liechtensteinische Kraftwerke

Location

Schaan, LIE

Identifier

CHE-271.508.945

Lots (1)

LOT-6731

Batteriespeichersystem (BESS) Balzers

Supply and commissioning of a BESS with minimum 25 MW / 50 MWh, delivered to Balzers, with a 12-month execution period and 120-month warranty/service phase. Main CPV 31440000 (Batteries). Additional CPVs include 31600000 (Electrical equipment), 31155000 (Inverters), 31170000 (Chargers), 72200000 (Software).

SuppliesEU fundedElectronic submissionSME suitable

Location

Balzers, Liechtenstein

Duration

Sep 2026

Category

Batteries

Selection criteria

Quality

Deadline

Deadline Jul 14, 2026

Procurement Details

Publication date
09 Jun 2026
Notice type
Contract notice — standard
Languages
German

Reference metadata

Notice subtype
17
Notice version
1
Legal basis
32014L0025

Reference IDs

Tender ID
398696-2026
Source notice ID
9c6e191c-8c90-41a1-b848-dcbe45e6b420

Documents (1)

Similar tenders