Project management for Enedis electrical networks construction

Enedis SA·Paris La Défense Cedex, France·EUR 27.1M·Expired · Jul 26, 2026·Neg W Call·Services·Framework
High valueStructured notice only
Oryginalny tytuł ogłoszenia

France – Engineering studies – Marche de maitrise d'œuvre déléguée pour la construction des réseaux électriques de distribution sous maitrise d’ouvrage Enedis - Direction Régionale Ile de France OUEST

60/100

Ocena szansy

Needs reviewHigh complexity
ServicesFrameworkExpired
Skąd ta ocena?

Szansa

60 / 100

Złożoność

75 / 100

Czynniki ryzyka

Procurement documents (technical specifications, contract terms, etc.) were not analyzed. Detailed requirements may aff...

The only award criterion disclosed is 'price is not the only criterion'; no weights or other criteria (e.g., quality, t...

No procurement documents available

Głęboka analiza portfolio

Głęboka analiza dopasowania firmy

Wykorzystuje:

  • Description
  • Industries & Services
  • Capabilities
  • Market & Experience
  • Certifications

Przegląd

Moderate opportunity

Kluczowe fakty

  • EUR 27.1M estimated value
  • Framework procurement
  • Services contract
  • 3 lots
  • Duration until May 2032
  • Delegated project management (maîtrise d'œuvre déléguée) for construction and maintenance of electrical distribution networks
  • Services related to specific agencies: ACE (electricity columns), ARMA (business connections), AIGP (large projects)
Pokaż pełne podsumowanie

This is a negotiated procedure under the Utilities Directive for delegated project management services related to the construction of electrical distribution networks for Enedis in the Île-de-France Ouest region. The contract is divided into three lots corresponding to different agencies (ACE, ARMA, AIGP) and is structured as framework agreements with a base duration of 48 months, extendable up to 72 months. The total estimated value is EUR 27,100,000. Only the TED XML notice was analyzed; procurement documents were not available.

Ryzyka

Procurement documents (technical specifications, contract terms, etc.) were not analyzed. Detailed requirements may aff...

The only award criterion disclosed is 'price is not the only criterion'; no weights or other criteria (e.g., quality, t...

No procurement documents available

Analiza może być niepełna

Przeanalizowano tylko część dokumentacji. Pozostałe dokumenty mogą zawierać dodatkowe wymagania, certyfikaty lub dokumenty do złożenia.

Kluczowe wymagania

Technical

  • Variant offers are not allowed
  • The contract is awarded through a negotiated procedure with prior call for competition

Administrative

  • Bidders may submit offers for one, two, or all three lots (maximum 3 lots)

Wymagania mogą być niepełne.

Kryteria udzielenia

Lot 1

Price (weight not specified); other criteria not provided

Lot 2

Price (weight not specified); other criteria not provided

Lot 3

Price (weight not specified); other criteria not provided

Zamawiający

Lokalizacja

Paris La Défense Cedex, FRA

Profil zamawiającego

Otwórz profil

Identyfikator

444 608 442

Działalność

Electricity-related activities

Części (3)

LOT-0001

ACE

Project management services for network construction related to the ACE agency (electricity columns agency). The lot is a framework agreement with an estimated value of EUR 6,346,000 and a framework maximum of EUR 7,932,500. Duration: 48 months firm, renewable twice for 12 months each (total up to 72 months). Includes a conditional tranche.

ServicesFrameworkEU fundedElectronic submission

EUR 27.1M

Szacowana wartość

Lokalizacja

FRZZZ, France

Czas trwania

Feb 2027 - May 2032

Kategoria

Electrical services

Kryteria udzielenia

Price

Termin

Expired Jul 26, 2026

LOT-0002

ARMA

Project management services for network construction related to the ARMA agency (business connection agency). Lot is a framework agreement with an estimated value of EUR 13,899,500 and a framework maximum of EUR 17,324,375. Duration: 48 months firm, renewable twice for 12 months each (total up to 72 months). Includes a conditional tranche.

ServicesFrameworkEU fundedElectronic submission

EUR 27.1M

Szacowana wartość

Lokalizacja

FRZZZ, France

Czas trwania

Feb 2027 - May 2032

Kategoria

Electrical services

Kryteria udzielenia

Price

Termin

Expired Jul 26, 2026

LOT-0003

AIGP

Project management services for network construction related to the AIGP agency (large projects engineering agency). Lot is a framework agreement with an estimated value of EUR 6,863,800 and a framework maximum of EUR 8,579,750. Duration: 48 months firm, renewable twice for 12 months each (total up to 72 months). Includes a conditional tranche.

ServicesFrameworkEU fundedElectronic submission

EUR 27.1M

Szacowana wartość

Lokalizacja

FRZZZ, France

Czas trwania

Feb 2027 - May 2032

Kategoria

Electrical services

Kryteria udzielenia

Price

Termin

Expired Jul 26, 2026

Szczegóły zamówienia

Data publikacji
29 Jun 2026
Języki
French

Metadane referencyjne

Podstawa prawna
32014L0025

Identyfikatory referencyjne

ID przetargu
445879-2026

Dokumenty (1)

Podobne przetargi