Construction of DN400 gas pipeline Mory-Reguły and adaptation for pigging of DN300/DN400 SG Mory-Gassy
Oryginalny tytuł ogłoszenia
Poland – Construction work for gas pipelines – Budowa gazociągu DN400 MOP 8,4 MPa relacji Mory-Reguły i przystosowanie do tłokowania gazociągu DN300/DN400 SG Mory-Gassy
Ocena szansy
Skąd ta ocena?
Szansa
40 / 100
Złożoność
70 / 100
Czynniki ryzyka
Strict financial criteria (minimum credit line of 4M PLN, average revenue 12.5M PLN, liquidity ratio ≥1.1) may disquali...
Specific experience requirement for pipeline ≥4km, ≥6.3MPa, ≥DN400, steel L415 may be difficult to meet for less experi...
No procurement documents available
Głęboka analiza portfolio
Wykorzystuje:
- Description
- Industries & Services
- Capabilities
- Market & Experience
- Certifications
Przegląd
Moderate opportunityKluczowe fakty
- Works contract
- 1 lot
- Duration until Oct 2028
- Construction of a gas pipeline DN400 with maximum operating pressure (MOP) of 8.4 MPa along the Mory-Reguły route.
- Adaptation of the existing DN300/DN400 gas pipeline SG Mory-Gassy for pigging operations.
Pokaż pełne podsumowanie
Tender by GAZ-SYSTEM S.A. for construction of a high-pressure gas pipeline (DN400, MOP 8.4 MPa) from Mory to Reguły, and adaptation of existing pipeline for pigging. Single lot, open procedure, price-only award. Estimated contract value not disclosed. Strict financial and technical eligibility criteria including minimum 4M PLN credit line, 12.5M PLN average revenue, and specific pipeline construction experience. Bid bond: 250,000 PLN. Deadline: 2026-07-15 10:00 CEST.
Ryzyka
Strict financial criteria (minimum credit line of 4M PLN, average revenue 12.5M PLN, liquidity ratio ≥1.1) may disquali...
Specific experience requirement for pipeline ≥4km, ≥6.3MPa, ≥DN400, steel L415 may be difficult to meet for less experi...
No procurement documents available
Analiza może być niepełna
Przeanalizowano tylko część dokumentacji. Pozostałe dokumenty mogą zawierać dodatkowe wymagania, certyfikaty lub dokumenty do złożenia.
Kluczowe wymagania
Technical
- Liquidity ratio (current assets / short-term liabilities) ≥ 1.10, or alternatively EBITDA > 0 and net debt/EBITDA ≤ 3.80.
Eligibility
- Financial standing: minimum 4,000,000 PLN credit line or own funds (not summable from different institutions for single bidder, but consortium members can combine).
- Average annual revenue of at least 12,500,000 PLN over last three fiscal years.
Kryteria udzielenia
Lot 1
Zamawiający
Lokalizacja
Warszawa, POL
Strona
Identyfikator
527-243-20-41
Działalność
Production, transport or distribution of gas or heat
Części (1)
LOT-0001
Construction of DN400 gas pipeline Mory-Reguły and adaptation for pigging of DN300/DN400 SG Mory-Gassy
Construction of a DN400 gas pipeline (MOP 8.4 MPa) and adaptation of existing pipeline for pigging. Requires specific technical expertise in high-pressure gas pipeline construction.
Lokalizacja
Czas trwania
Kategoria
Kryteria udzielenia
Termin
Szczegóły kryteriów
Cena całkowita brutto oferty - waga 100%
Uwaga do wartości
Pokaż oryginalne dane TED
Oryginalny tytuł części
Budowa gazociągu DN400 MOP 8,4 MPa relacji Mory-Reguły i przystosowanie do tłokowania gazociągu DN300/DN400 SG Mory-Gassy.
Oryginalny opis TED
Budowa gazociągu DN400 MOP 8,4 MPa relacji Mory-Reguły i przystosowanie do tłokowania gazociągu DN300/DN400 SG Mory-Gassy.
Szczegóły zamówienia
- Data publikacji
- 24 Jun 2026
- Języki
- Polish
Metadane referencyjne
- Podstawa prawna
- 32014L0025
Identyfikatory referencyjne
- ID przetargu
- 432328-2026
Dokumenty (1)
Podobne przetargi
Ocena szansy
Skąd ta ocena?
Szansa
40 / 100
Złożoność
70 / 100
Czynniki ryzyka
Strict financial criteria (minimum credit line of 4M PLN, average revenue 12.5M PLN, liquidity ratio ≥1.1) may disquali...
Specific experience requirement for pipeline ≥4km, ≥6.3MPa, ≥DN400, steel L415 may be difficult to meet for less experi...
No procurement documents available
Głęboka analiza portfolio
Wykorzystuje:
- Description
- Industries & Services
- Capabilities
- Market & Experience
- Certifications