Tenderwize
Retour à la recherche

Reconstruction of Miłosław 110/15 kV Substation

ENEA Operator sp. z o.o.·Poznań, Poland·EUR 5.4M·Expired · Jul 16, 2026·Open·Works
High value
Titre original de l'avis

Poland – Construction work – Przebudowa stacji 110/15 kV Miłosław [MAW], S-2025-12626

49/100

Score d'opportunité

Needs reviewHigh complexity
WorksExpired
Pourquoi ce score ?

Opportunité

49 / 100

Complexité

72 / 100

Facteurs de risque

The notice text shows the bid deadline was changed from 14 July 2026 10:00 to 16 July 2026 10:00, which creates a timin...

The selection criteria require substantial prior experience, insurance, liquidity and a scoring threshold, which may di...

No procurement documents available

Analyse approfondie du portefeuille

Analyse approfondie de l'adéquation entreprise

Utilise:

  • Description
  • Industries & Services
  • Capabilities
  • Market & Experience
  • Certifications

Informations clés

Pouvoir adjudicateur
ENEA Operator sp. z o.o.
Pays
Pologne
CPV
45000000 - Construction work +21 autres
Date limite
Jul 16, 2026
Valeur estimée
EUR 5.4M

Aperçu

Moderate opportunity

Faits clés

  • EUR 5.4M estimated value
  • Works contract
  • 1 lot
  • Duration 100 WEEK
  • Turnkey reconstruction of a 110/15 kV substation in Miłosław.
  • Design, supply, installation and commissioning are included.
Afficher le résumé complet

Open works contract for turnkey reconstruction of the 110/15 kV Miłosław substation in Poland, with design, delivery, installation and commissioning included. One lot is present. Submission is electronic and the deadline was extended to 16 July 2026 at 10:00 local time. Award is price-only, but the selection criteria are demanding: OC insurance of at least PLN 8,000,000, financing capacity of at least PLN 8,000,000, a scoring level of at least 3.75, relevant 110 kV substations experience, and ISO/IEC 27001-based information security arrangements.

Risques

The notice text shows the bid deadline was changed from 14 July 2026 10:00 to 16 July 2026 10:00, which creates a timin...

The selection criteria require substantial prior experience, insurance, liquidity and a scoring threshold, which may di...

No procurement documents available

L'analyse peut être incomplète

Seule une partie des documents de consultation a été analysée. Des exigences, certificats ou documents de soumission supplémentaires peuvent exister dans les documents restants.

Exigences clés

Technical

  • Variants are not allowed.
  • Contract duration is 100 weeks.

Administrative

  • Electronic submission is required.

Critères d'attribution

Lot 1

Price only, 100% — 100%

Acheteur

Localisation

Poznań, POL

Profil acheteur

Ouvrir le profil

Identifiant

7822377160

Activité

Electricity-related activities

Lots (1)

LOT-0001

Reconstruction of Miłosław 110/15 kV Substation

Turnkey reconstruction of the Miłosław 110/15 kV substation, including design, supply, installation and commissioning. The scope explicitly requires obtaining all permits, approvals, decisions and consents required by law. The document text also indicates the design must follow the SWZ and PFU, and the Enea distribution network standards for unspecified parts.

WorksElectronic submissionSME suitable

Localisation

Miłosław, Poland

Durée

100 WEEK

Catégorie

Construction work

Critères d'attribution

Price

Date limite

Expired Jul 16, 2026

Détails de la procédure

Date de publication
08 Jul 2026
Langues
Polish

Métadonnées de référence

Base juridique
32014L0025

Identifiants de référence

ID de l'appel d'offres
475273-2026

Documents (1)