Selection of contractor for construction of the Mother and Child Pavilion

Oblastní nemocnice Mladá Boleslav, a.s., nemocnice Středočeského kraje·Mladá Boleslav, Czech Republic·CZK 1136.6M | EUR 47M·Expired · Aug 18, 2026·Open·Works
High valueStructured notice only
Titre original de l'avis

Czechia – Construction work – Výběr zhotovitele stavby Pavilonu pro matku a dítě

65/100

Score d'opportunité

PromisingHigh complexity
WorksExpired
Pourquoi ce score ?

Opportunité

65 / 100

Complexité

75 / 100

Facteurs de risque

Construction must occur while hospital remains fully operational; any disruption could lead to penalties or work stoppa...

Blower Door test by 31 July 2028 is a hard deadline with specific air permeability requirement (n50 ≤ 0.6 h-1). Failure...

Analyse approfondie du portefeuille

Analyse approfondie de l'adéquation entreprise

Utilise:

  • Description
  • Industries & Services
  • Capabilities
  • Market & Experience
  • Certifications

Informations clés

Pouvoir adjudicateur
Oblastní nemocnice Mladá Boleslav, a.s., nemocnice Středočeského kraje
Pays
République tchèque
CPV
45000000 - Construction work +4 autres
Date limite
Aug 18, 2026
Valeur estimée
CZK 1136.6M (approx. EUR 47M)

Aperçu

Strong opportunity

Faits clés

  • CZK 1136.6M estimated value
  • Works contract
  • 1 lot
  • Duration 1000 DAY
  • Site preparation and demolition (SO 00, SO 00.1, SO 10)
  • Building B - only medical gases (SO 01)
Afficher le résumé complet

Construction of a mother and child pavilion at Klaudiánova nemocnice in Mladá Boleslav, Czechia. The project includes multiple building and engineering objects such as site preparation, building works, utility relocations, and landscaping. Work must be carried out while the hospital remains operational. Key milestones: Blower Door test by 31 July 2028, cooling and heating reconnections during summer outages. EU funded. Single lot. Estimated value CZK 1,136,557,000. Open procedure, electronic submission required. Deadline: 18 August 2026.

Risques

Construction must occur while hospital remains fully operational; any disruption could lead to penalties or work stoppa...

Blower Door test by 31 July 2028 is a hard deadline with specific air permeability requirement (n50 ≤ 0.6 h-1). Failure...

L'analyse peut être incomplète

Seule une partie des documents de consultation a été analysée. Des exigences, certificats ou documents de soumission supplémentaires peuvent exister dans les documents restants.

Exigences clés

Technical

  • Work must be performed while the hospital is fully operational; no disruption to patient care allowed.
  • Mandatory milestone: Blower Door test (air permeability n50 ≤ 0.6 h-1) by 31 July 2028.
  • Cooling system reconnection must occur during suitable climatic and operational conditions to avoid disruption.

Les exigences peuvent être incomplètes.

Critères d'attribution

Lot 1

Price 100% — 100%

Acheteur

Localisation

Mladá Boleslav, CZE

Profil acheteur

Ouvrir le profil

Identifiant

27256456

Activité

Health

Lots (1)

LOT-0001

Selection of contractor for construction of the Mother and Child Pavilion

Construction of the Mother and Child Pavilion at Klaudiánova nemocnice including all building objects, engineering objects, and related works. The project must be executed while the hospital remains fully operational.

WorksEU fundedElectronic submission

EUR 47M

Valeur estimée

Localisation

CZ020, Czech Republic

Durée

1000 DAY

Catégorie

Construction work

Critères d'attribution

Price

Date limite

Expired Aug 18, 2026

Détails de la procédure

Date de publication
06 Jul 2026
Langues
Czech

Métadonnées de référence

Base juridique
32014L0024

Identifiants de référence

ID de l'appel d'offres
465322-2026