Tenderwize
Retour à la recherche

Construction de la station d'épuration de Villers-l'Evêque

AIDE·Saint-Nicolas, Belgium·Expired · Oct 27, 2026·Open·Works
Titre original de l'avis

Belgium – Sewage-treatment plant construction work – Awans - Construction de la station d'épuration de Villers-l'Evêque

57/100

Score d'opportunité

Needs reviewHigh complexity
WorksExpired
Pourquoi ce score ?

Opportunité

57 / 100

Complexité

72 / 100

Facteurs de risque

The required aggregation under the Law of 20 March 1991 must be held by the contractor and every consortium member at b...

The structured data specifies 250 days, while the XML notice also contains a 180-day duration field. The applicable con...

Analyse approfondie du portefeuille

Analyse approfondie de l'adéquation entreprise

Utilise:

  • Description
  • Industries & Services
  • Capabilities
  • Market & Experience
  • Certifications

Informations clés

Pouvoir adjudicateur
AIDE
Pays
Belgique
CPV
45252100 - Sewage-treatment plant construction work +1 autres
Date limite
Oct 27, 2026

Aperçu

Moderate opportunity

Faits clés

  • Works contract
  • 1 lot
  • Duration 250 DAY
  • Construction of a wastewater treatment plant for urban wastewater in Villers-l'Evêque, within Awans, Belgium.
  • Treatment capacity of 6,430 population equivalent.
Afficher le résumé complet

Open procedure for construction of a municipal wastewater treatment plant in Villers-l'Evêque, Awans, Belgium. The plant is designed for 6,430 population equivalent, using low-load activated sludge treatment and mechanical dewatering of excess sludge. Electronic submission is required through publicprocurement.be. The structured data identifies one lot, a 250-day duration, and an aggregation requirement under the Belgian Law of 20 March 1991. No contract value is available. Linked procurement documents are available, but their contents were not provided for analysis.

Risques

The required aggregation under the Law of 20 March 1991 must be held by the contractor and every consortium member at b...

The structured data specifies 250 days, while the XML notice also contains a 180-day duration field. The applicable con...

L'analyse peut être incomplète

Seule une partie des documents de consultation a été analysée. Des exigences, certificats ou documents de soumission supplémentaires peuvent exister dans les documents restants.

Exigences clés

Technical

  • The contract is for works under an open procedure.
  • The structured data specifies a 250-day contract duration.

Administrative

Critères d'attribution

Lot 1

Quality: technical value of the works — 45% — 45%Cost: investment cost — 45% — 45%Quality: quality and precision of the equipment — 10% — 10%

Acheteur

Nom

AIDE

Localisation

Saint-Nicolas, BEL

Site web

www.aide.be/

Profil acheteur

Ouvrir le profil

Identifiant

0203.963.680

Activité

General public services

Lots (1)

LOT-0001

Awans wastewater treatment plant construction

Construction of a 6,430-population-equivalent urban wastewater treatment plant in Villers-l'Evêque, Awans, including low-load activated sludge treatment and mechanical dewatering of excess sludge. The structured data specifies a 250-day duration and demolition work as an additional classification.

WorksEU fundedElectronic submission

Localisation

AWANS, Belgium

Durée

250 DAY

Catégorie

Sewage-treatment plant construction work

Critères d'attribution

Quality

Date limite

Expired Oct 27, 2026

Détails de la procédure

Date de publication
01 Jul 2026
Langues
French

Métadonnées de référence

Base juridique
32014L0024

Identifiants de référence

ID de l'appel d'offres
455235-2026

Documents (2)

Appels d'offres similaires

Cookies & Privacy

With your consent, we use Google Analytics, Microsoft Clarity (session recordings) and Google Ads cookies to understand how Tenderwize is used and to measure our advertising. You can change your choice at any time via “Cookie Settings” in the footer. Cookie Policy · Privacy Policy