Design and Build of S19 Expressway Section Lot 1

Generalna Dyrekcja Dróg Krajowych i Autostrad·Lublin, Poland·Expired · Jul 13, 2026·Open·Works
Titre original de l'avis

Poland – Construction, foundation and surface works for highways, roads – Projekt i budowa drogi ekspresowej S19 odcinek granica woj. podlaskiego – Łosice – granica woj. lubelskiego, odc. realizacyjny nr 1 granica woj. podlaskiego - węzeł Łosice (bez węzła)

60/100

Score d'opportunité

Needs reviewHigh complexity
WorksExpired
Pourquoi ce score ?

Opportunité

60 / 100

Complexité

85 / 100

Facteurs de risque

High revenue and credit requirements may exclude many contractors.

Mandatory personal execution of pavement works limits reliance on specialized subcontractors.

Analyse approfondie du portefeuille

Analyse approfondie de l'adéquation entreprise

Utilise:

  • Description
  • Industries & Services
  • Capabilities
  • Market & Experience
  • Certifications

Aperçu

Moderate opportunity

Faits clés

  • Works contract
  • 1 lot
  • Duration 47 MONTH
  • Design and construction of ~17.263 km of dual-carriageway expressway (class S)
  • Construction of one road junction
Afficher le résumé complet

Design and build of the S19 expressway section (approx. 17.263 km) in Mazowieckie, Poland, including junctions, bridges, service areas, environmental protection, and road infrastructure. The contract covers full design and construction with a 47-month duration. The tender requires a minimum average annual revenue of 215M PLN, financial capacity of 60M PLN, and specific experience in road and bridge construction. The contractor must personally execute key pavement works and cannot rely on third-party resources for those tasks. EU-funded, open procedure. Estimated value above 20M EUR.

Risques

High revenue and credit requirements may exclude many contractors.

Mandatory personal execution of pavement works limits reliance on specialized subcontractors.

L'analyse peut être incomplète

Seule une partie des documents de consultation a été analysée. Des exigences, certificats ou documents de soumission supplémentaires peuvent exister dans les documents restants.

Exigences clés

Technical

  • Bid bond of 7,000,000 PLN required.
  • Performance bond of 10% of contract price required.

Administrative

  • Contractor must personally perform key tasks: main road pavement including production and laying of all layers above native ground; cannot rely on third-party resources for...

Critères d'attribution

Lot 1

Price criterion with 60% weight60%Quality criterion: Bridge warranty extension (30%)30%Quality criterion: Noise barrier & equipment warranty extension (10%)10%

Acheteur

Localisation

Lublin, POL

Identifiant

8971770779

Activité

General public services

Lots (1)

LOT-0001

Design and Build of S19 Expressway Section Lot 1

Design and construction of the S19 expressway from the border of Podlaskie Voivodeship to Łosice junction (excluding the junction), covering ~17.263 km of dual carriageway, junctions, service areas, bridges, environmental measures, and associated road infrastructure.

WorksEU fundedElectronic submission

Localisation

PL814, Poland

Durée

47 MONTH

Catégorie

Construction

Critères d'attribution

Best price-quality ratio

Date limite

Expired Jul 13, 2026

Détails de la procédure

Date de publication
14 Jun 2026
Langues
Polish

Métadonnées de référence

Base juridique
32014L0024

Identifiants de référence

ID de l'appel d'offres
406342-2026

Documents (1)

Appels d'offres similaires