Tenderwize
Back to tender search

High-Performance Computing Cluster for Research Project

Universitat de Barcelona·No consta, Spain·Expired · Jul 20, 2026·Open·Supplies
Original notice title

Spain – Data-processing machines (hardware) – 2026/31 98 Cluster de computación de alto rendimiento para el proyecto de investigación "Red Teaming the HO tension "REDHOT"

52/100

Opportunity Score

Needs reviewHigh complexity
SuppliesExpired
Why this score?

Opportunity

52 / 100

Complexity

82 / 100

Risk factors

The notice provides high-level HPC requirements but does not specify detailed performance benchmarks, GPU models or qua...

No estimated value or budget is available, so the required solution scale cannot be compared with the likely commercial...

Deep Portfolio Analysis

Deep Company Fit Analysis

Uses:

  • Description
  • Industries & Services
  • Capabilities
  • Market & Experience
  • Certifications

Tender facts

Contracting authority
Universitat de Barcelona
Country
Spain
CPV
30210000 - Data-processing machines (hardware)
Deadline
Jul 20, 2026

Overview

Moderate opportunity

Key Facts

  • Supplies contract
  • 1 lot
  • Duration 45 DAY
  • Supply, install, configure and commission a high-performance computing cluster.
  • Provide at least 3,072 computing cores based on four high-density chassis, with capacity for four compute servers in a 2U space.
Show full summary

Open procedure for the supply, installation, configuration and commissioning of one high-performance computing cluster for the REDHOT research project of the Universitat de Barcelona. The solution must provide at least 3,072 computing cores and include CPU/GPU compute nodes, high-performance storage, login nodes, high-speed communications, technical racks with advanced cooling, HPC software, and auxiliary electrical/data interconnection equipment. The tender is EU-funded and requires electronic submission. Procurement documents are referenced, but the underlying procurement dossier was not analyzed; only the TED XML notice text was available.

Risks

The notice provides high-level HPC requirements but does not specify detailed performance benchmarks, GPU models or qua...

No estimated value or budget is available, so the required solution scale cannot be compared with the likely commercial...

Analysis may be incomplete

Only part of the procurement documentation was analyzed. Additional eligibility requirements, certificates, or submission documents may exist in the remaining tender documentation.

Key Requirements

Technical

  • The contract is for supplies and includes installation, configuration and commissioning.
  • The cluster must provide at least 3,072 computing cores.
  • The solution must include CPU and GPU compute capability, storage, login nodes, high-speed communications, racks, cooling, HPC software, and auxiliary interconnection equipment.

Buyer

Location

No consta, ESP

Website

www.ub.edu

Identifier

4661470

Activity

Education

Lots (1)

LOT-0000

High-Performance Computing Cluster for the REDHOT Research Project

Single lot covering the integrated supply, installation, configuration and commissioning of an HPC cluster with at least 3,072 computing cores, four high-density chassis capable of housing four compute servers in 2U, CPU/GPU compute nodes, storage, login nodes, communications, cooling infrastructure, HPC software, and auxiliary connections. The lot is performed in Barcelona, Spain.

SuppliesEU fundedElectronic submission

Location

ES511, Spain

Duration

45 DAY

Category

Data-processing machines

Deadline

Expired Jul 20, 2026

Procurement Details

Publication date
08 Jul 2026
Languages
Spanish, Cat

Reference metadata

Legal basis
32014L0024

Reference IDs

Tender ID
473931-2026

Documents (1)

Similar tenders

Cookies & Privacy

With your consent, we use Google Analytics, Microsoft Clarity (session recordings) and Google Ads cookies to understand how Tenderwize is used and to measure our advertising. You can change your choice at any time via “Cookie Settings” in the footer. Cookie Policy · Privacy Policy