Sludge Digestion Replacement and EMSR Works
Original notice title
Germany – Sewage digesters – Ersatzneubau der Schlammfaulung Los 3 - EMSR-Technik
Opportunity Score
Why this score?
Opportunity
58 / 100
Complexity
72 / 100
Risk factors
The submission deadline is fixed and relatively near; missing it would invalidate the bid.
Works must be carried out during continuous plant operation, which can constrain methods, sequencing, and safety planni...
Deep Portfolio Analysis
Uses:
- Description
- Industries & Services
- Capabilities
- Market & Experience
- Certifications
Overview
Moderate opportunityKey Facts
- Works contract
- 1 lot
- Duration until Jan 2029
- Replacement/new construction of sludge digestion facilities.
- Construction of a new digester and new biogas treatment.
Show full summary
Open works tender by Stadt Cloppenburg for the replacement/new construction of sludge digestion facilities (Lot 1 / LOT-0000) in Cloppenburg, Germany. The scope covers a new digester, biogas treatment, CHP plant, machine building, and process/electrical/control integration while keeping the plant in continuous operation. Submission is electronic and the deadline is 2026-08-12 10:30 local time. No contract value is provided in the structured data or XML notice.
Risks
The submission deadline is fixed and relatively near; missing it would invalidate the bid.
Works must be carried out during continuous plant operation, which can constrain methods, sequencing, and safety planni...
Analysis may be incomplete
Only part of the procurement documentation was analyzed. Additional eligibility requirements, certificates, or submission documents may exist in the remaining tender documentation.
Key Requirements
Technical
- Open procedure.
- Award criterion is price only, weighted at 100%.
Administrative
- Electronic submission is allowed.
Award Criteria
Lot 1
Buyer
Location
Cloppenburg, DEU
Identifier
034530004004-0-35
Activity
General public services
Lots (1)
LOT-0000
Sludge Digestion Replacement and EMSR Works
Works for the replacement/new construction of sludge digestion facilities, including a new digester, new biogas treatment, a CHP plant with 2 modules expandable to 3, a machine building for plant and electrical/instrumentation/control technology, integration with the existing plant, and adaptation/extension of the control system. The works are to be carried out during continuous plant operation.
Location
Duration
Category
Award Criteria
Deadline
Award details
Der Zuschlag wird auf das wirtschaftlichste Angebot erteilt.
Value note
Show original TED data
Original lot title
Ersatzneubau der Schlammfaulung Los 3 - EMSR-Technik
Original TED description
Der Leistungsumfang zum Neubau der Faulung stellt sich wie folgt dar: · Erneuerung bzw. Bau einer neuen Faulung · Bau einer neuen Faulgasaufbereitung · Errichtung einer BHKW-Anlage bestehend aus 2 Modulen (erweiterungsfähig auf 3) · Maschinengebäude für Anlagen- und E-MSR-Technik · Verfahrens-, elektro- und leittechnische Anbindung an den Anlagenbestand · Anpassung und Ergänzung des Leitsystems bezogen auf den Neubau bzw. Zubau eines zweiten Faulbehälters auf der Kläranlage · Errichtung bei durchgehendem Anlagenbetrieb
Procurement Details
- Publication date
- 06 Jul 2026
- Languages
- German
Reference metadata
- Legal basis
- 32014L0024
Reference IDs
- Tender ID
- 466640-2026
Documents (1)
Opportunity Score
Why this score?
Opportunity
58 / 100
Complexity
72 / 100
Risk factors
The submission deadline is fixed and relatively near; missing it would invalidate the bid.
Works must be carried out during continuous plant operation, which can constrain methods, sequencing, and safety planni...
Deep Portfolio Analysis
Uses:
- Description
- Industries & Services
- Capabilities
- Market & Experience
- Certifications