Poland – Public-service buses – Dostawa fabrycznie nowych, niskopodłogowych autobusów miejskich o napędzie elektrycznym wraz z ładowarkami w ramach projektu pn. „Zeroemisyjne autobusy dla zrównoważonej mobilności Koszalina – etap II"

50/100

Opportunity Score

Needs reviewHigh complexity
SuppliesExpired
Why this score?

Opportunity

50 / 100

Complexity

85 / 100

Risk factors

No estimated value published; bidders cannot assess affordability or compare with budget. May lead to bid rejection if...

Short submission deadline (25 days) for a technically complex tender. Risk of incomplete or erroneous submission.

Deep Portfolio Analysis

Deep Company Fit Analysis

Uses:

  • Description
  • Industries & Services
  • Capabilities
  • Market & Experience
  • Certifications

Overview

Moderate opportunity

Key Facts

  • Supplies contract
  • 1 lot
  • Duration until Mar 2028
  • Production and delivery of 7 MAXI (11.5-12.5m) low-floor electric buses
  • Production and delivery of 6 MEGA (17.5-18.5m) low-floor electric buses
Show full summary

This is an open tender for the supply of 13 new low-floor electric city buses (7 MAXI and 6 MEGA), 13 fixed chargers, 1 mobile charger, and 1 emergency generator (0.5 MW) for the city of Koszalin, Poland. The contract is EU-funded under the FENX.03.01 program. The procurement is a single lot with no lot division. The deadline for submission is 31 July 2026 at 08:00 CEST. The estimated contract value is not disclosed. Award criteria: price (60%), technical parameters (35%), and shortening of delivery time (5%). Eligibility requires proven delivery of at least two contracts of 10+ new electric city buses each in the last 3 years. Bidders must submit a bid bond of PLN 450,000. The tender documents are available on the e-Zamówienia platform. Only Polish language is used.

Risks

No estimated value published; bidders cannot assess affordability or compare with budget. May lead to bid rejection if...

Short submission deadline (25 days) for a technically complex tender. Risk of incomplete or erroneous submission.

Analysis may be incomplete

Only part of the procurement documentation was analyzed. Additional eligibility requirements, certificates, or submission documents may exist in the remaining tender documentation.

Key Requirements

Technical

  • Bidders must have delivered at least two contracts of min. 10 new electric city buses each within the last 3 years
  • Bid bond of PLN 450,000 required
  • No variants allowed

Award Criteria

Lot 1

Price 60%60%Technical parameters 35% (11 sub-criteria)35%Shortening delivery time 5%5%

Buyer

Location

Koszalin, POL

Buyer profile

Open profile

Identifier

330002466

Activity

General public services

Lots (1)

LOT-0001

Supply of new low-floor electric city buses with chargers

Supply of 7 MAXI (11.5-12.5m) and 6 MEGA (17.5-18.5m) electric buses, 13 fixed chargers, 1 mobile charger, and 1 emergency generator (0.5 MW). Scope includes production, delivery, installation, and commissioning. Detailed technical specifications in the contract and annexes. Part of the 'Zero-emission buses for sustainable mobility of Koszalin - phase II' project.

SuppliesEU fundedElectronic submission

Location

Koszalin, Poland

Duration

Oct 2026 - Mar 2028

Category

Public-service buses

Award Criteria

Price

Deadline

Expired Jul 31, 2026

Procurement Details

Publication date
05 Jul 2026
Languages
Polish

Reference metadata

Legal basis
32014L0024

Reference IDs

Tender ID
463930-2026

Documents (1)

Similar tenders