Reconstruction of water supply main Koszalin-Mielno – task III

Ekoprzedsiębiorstwo Sp. z o.o.·Mielno, Poland·Expired · Jul 27, 2026·Open·Works
Structured notice only
Original notice title

Poland – Works related to water-distribution pipelines – Przebudowa (modernizacja) istniejącej magistrali wodociągowej Koszalin-Mielno – zadanie III

50/100

Opportunity Score

Needs reviewHigh complexity
WorksExpired
Why this score?

Opportunity

50 / 100

Complexity

70 / 100

Risk factors

No estimated value disclosed; bidders cannot assess budget or required financial capacity.

Only the notice was analyzed; crucial documents (SWZ, contract terms, technical specifications) were not examined.

Deep Portfolio Analysis

Deep Company Fit Analysis

Uses:

  • Description
  • Industries & Services
  • Capabilities
  • Market & Experience
  • Certifications

Tender facts

Contracting authority
Ekoprzedsiębiorstwo Sp. z o.o.
Country
Poland
CPV
45232150 - Works related to water-distribution pipelines +7 more
Deadline
Jul 27, 2026

Overview

Moderate opportunity

Key Facts

  • Works contract
  • 1 lot
  • Duration 180 DAY
  • Reconstruction of DN400 asbestos-cement water main with DN315 PE100 RC SDR17 using trenchless relining (approx. 2,118 m)
  • Modernization of existing chambers XVI and XVII, construction of new chamber KZ-4 with prefabricated reinforced concrete elements DN2500
Show full summary

This tender is an open procedure for the reconstruction of a water supply main (DN400 asbestos-cement to PE100 RC DN315) over approximately 2,118 m using trenchless relining, along with chamber modernization, electrical and AKPiA works, and site restoration. The project is EU-funded (FENX 2021-2027) and located in Koszalin, Będzino, and Mielno, Poland. The contracting authority is Ekoprzedsiębiorstwo Sp. z o.o. The tender is 100% price-based with a 22-day submission deadline (27 July 2026). No estimated value is provided. Only the TED notice was analyzed; procurement documents were not examined.

Risks

No estimated value disclosed; bidders cannot assess budget or required financial capacity.

Only the notice was analyzed; crucial documents (SWZ, contract terms, technical specifications) were not examined.

Analysis may be incomplete

Only part of the procurement documentation was analyzed. Additional eligibility requirements, certificates, or submission documents may exist in the remaining tender documentation.

Key Requirements

Technical

  • Bid bond of 90,000 PLN required
  • Performance bond: 5% of total contract price (gross)

Administrative

  • Tender must be submitted electronically via Platforma e-Zamówienia

Requirements may be incomplete.

Award Criteria

Lot 1

Price criterion with 100% weight (lowest price wins). — 100%

Buyer

Location

Mielno, POL

Identifier

4990555465

Activity

Water-related activities

Lots (1)

LOT-0001

Reconstruction of water supply main Koszalin-Mielno – task III

Reconstruction of a DN400 asbestos-cement water supply main by installing a DN315 PE100 RC SDR17 pipeline via relining (approx. 2118 m), modernization of chambers XVI and XVII, construction of a new chamber KZ-4, installation of valves, flow meters, electrical and control systems, site development, and as-built documentation.

WorksEU fundedElectronic submission

Location

PL426, Poland

Duration

180 DAY

Category

Works related to water-distribution…

Award Criteria

Price

Deadline

Expired Jul 27, 2026

Procurement Details

Publication date
05 Jul 2026
Languages
Polish

Reference metadata

Legal basis
32014L0025

Reference IDs

Tender ID
463875-2026

Documents (1)