Railway Bridge Construction and Demolition

C.N.C.F "C.F.R." S.A. - SUCURSALA REGIONALĂ C.F. BRAȘOV - UNITATE OPERAȚIONALĂ·Brasov, Romania·RON 75.1M | EUR 14.3M·Expired · Jul 31, 2026·Open·Works
High valueStructured notice only
Original notice title

Romania – Railway bridge construction work – ”POD CF NOU KM 317+950, LINIA CF DEDA – RĂZBOIENI ȘI DEMOLAREA PODULUI CF EXISTENT (EXECUŢIE)“ SRCF BRAȘOV

40/100

Opportunity Score

Needs reviewMedium complexity
WorksExpired
Why this score?

Opportunity

40 / 100

Complexity

60 / 100

Risk factors

Contract signing is conditional on funding approval. If not obtained within 12 months, procedure may be canceled withou...

Deadline time differs between structured data (12:00) and XML (15:00). Also EU funding flag inconsistency (structured...

Deep Portfolio Analysis

Deep Company Fit Analysis

Uses:

  • Description
  • Industries & Services
  • Capabilities
  • Market & Experience
  • Certifications

Overview

Moderate opportunity

Key Facts

  • RON 75.1M estimated value
  • Works contract
  • 1 lot
  • Duration 20 MONTH
  • Construction of a new railway bridge (170.10 m total length, 2 spans of 80 m each)
  • Demolition of existing railway bridge
Show full summary

This is an open procedure for the construction of a new railway bridge at km 317+950 on the Deda–Războieni line, including demolition of the existing bridge. The contract is for works, with an estimated value of 75,106,506.88 RON (approx. 14.3M EUR). The contracting authority is C.N.C.F "C.F.R." S.A. - Sucursala Regională C.F. Brașov. The procedure is subject to a suspensive clause: contract signing depends on funding approval, which may take up to 12 months. Submission deadline is 31 July 2026. Award is based on price (95%) and warranty period (5%).

Risks

Contract signing is conditional on funding approval. If not obtained within 12 months, procedure may be canceled withou...

Deadline time differs between structured data (12:00) and XML (15:00). Also EU funding flag inconsistency (structured...

Analysis may be incomplete

Only part of the procurement documentation was analyzed. Additional eligibility requirements, certificates, or submission documents may exist in the remaining tender documentation.

Key Requirements

Technical

  • DUAE must be completed by all bidders, associates, and subcontractors
  • Bid bond required (guarantee type code true)

Administrative

  • Electronic submission via SEAP (required)

Requirements may be incomplete.

Award Criteria

Lot 1

Price criterion (95%)95%Warranty period (5%)5%

Buyer

Location

Brasov, ROU

Website

www.cfr.ro

Buyer profile

Open profile

Identifier

15509275

Activity

Railway services

Lots (1)

LOT-0000

Railway Bridge Construction and Demolition

Construction of a new railway bridge (total length 170.10 m, two spans of 80 m each), a level crossing, and railway line in definitive route of 1200 m. Demolition of existing bridge. Duration 20 months, with possible extension up to 4 months per year due to cold weather.

WorksEU fundedElectronic submission

EUR 14.3M

Estimated value

Location

RO122, Romania

Duration

20 MONTH

Category

Railway bridge construction work

Award Criteria

Price

Deadline

Expired Jul 31, 2026

Procurement Details

Publication date
21 Jun 2026
Languages
Romanian

Reference metadata

Legal basis
32014L0025

Reference IDs

Tender ID
426137-2026

Documents (2)