Transmission line construction work

E.ON Észak-dunántúli Áramhálózati Zrt.·Győr, Hungary·Expired · Aug 10, 2026·Open·Works
Structured notice only
Originaltitel der Bekanntmachung

Hungary – Construction work – Távvezeték-kivitelezés IV. ütem – 3 részben (ism.)

62/100

Opportunity Score

Needs reviewHigh complexity
WorksExpired
Warum diese Bewertung?

Chance

62 / 100

Komplexität

78 / 100

Risikofaktoren

The structured data deadline is 2026-08-10 09:00 UTC, while the XML notice shows EndTime 11:00:00+02:00, which is consi...

Procurement documents are referenced by URL, but no extracted document text was provided, so the contract draft and tec...

Tiefe Portfolioanalyse

Tiefe Analyse der Unternehmenspassung

Verwendet:

  • Description
  • Industries & Services
  • Capabilities
  • Market & Experience
  • Certifications

Überblick

Moderate opportunity

Wichtige Fakten

  • Works contract
  • 3 lots
  • Construction of a 132 kV transmission line between Zirc and Észak-Litér in three separate lots.
  • Lot 1: foundation works for transmission line towers, including archaeological excavation and full demining.
Vollständige Zusammenfassung anzeigen

This is an open works tender for the construction of the Zirc–Észak-Litér 132 kV overhead line in 3 lots: foundations, tower erection/assembly, and wiring/ground cable laying. The notice is in Hungarian, electronic submission is required, and the deadline is 2026-08-10 09:00 UTC. No contract value is provided in the structured data or XML. The tender has explicit technical and professional eligibility requirements, including references, staff qualifications, registry membership, insurance, HSE, and quality/environment systems. Procurement documents are available via EKR, but no extracted procurement document text was provided, so they were not analyzed.

Risiken

The structured data deadline is 2026-08-10 09:00 UTC, while the XML notice shows EndTime 11:00:00+02:00, which is consi...

Procurement documents are referenced by URL, but no extracted document text was provided, so the contract draft and tec...

Analyse kann unvollständig sein

Nur ein Teil der Vergabeunterlagen wurde analysiert. Weitere Anforderungen, Zertifikate oder Einreichungsdokumente können in den übrigen Unterlagen enthalten sein.

Wichtige Anforderungen

Technical

  • The contractor must provide a technical-financial schedule.

Administrative

  • Electronic submission is required.
  • The notice language is Hungarian.

Anforderungen können unvollständig sein.

Zuschlagskriterien

Lot 1

Quality criterion: additional warranty period, weight 15, weight code poi-exa.15%

Lot 2

Quality criterion: expert experience beyond eligibility, weight 15, weight code poi-exa.15%

Lot 3

Price criterion: net contract price excluding reserve fund, weight 70, weight code poi-exa.70%

Auftraggeber

Ort

Győr, HUN

Auftraggeberprofil

Profil öffnen

Kennung

10741980208

Tätigkeit

Electricity-related activities

Lose (3)

LOT-0001

Foundations for Zirc–Észak-Litér line

Lot 1 covers construction of foundation works for the 132 kV Zirc–Észak-Litér transmission line. The scope includes use of buyer-provided materials/equipment from the technical specification, procurement of missing materials by the contractor, complete archaeological excavation work, and full demining. The route crosses several Veszprém county settlements. The lot duration is 140 working days, excluding 15 December to 15 January.

WorksEU fundedElectronic submissionSME suitable

Ort

Zirc Észak-Litér közötti nyomvonal, Hungary

Dauer

140 DAY

Kategorie

Site preparation work

Zuschlagskriterien

Quality

Frist

Expired Aug 10, 2026

LOT-0002

Tower erection and assembly for Zirc–Észak-Litér line

Lot 2 covers tower erection and assembly works for the 132 kV Zirc–Észak-Litér transmission line. The contractor must use buyer-provided materials/equipment from the technical specification and procure any missing materials/equipment. The route crosses several Veszprém county settlements. The lot duration is 122 working days, excluding 15 December to 15 January.

WorksEU fundedElectronic submissionSME suitable

Ort

Zirc Észak-Litér közötti nyomvonal, Hungary

Dauer

122 DAY

Kategorie

Assembly of metal structures

Zuschlagskriterien

Quality

Frist

Expired Aug 10, 2026

LOT-0003

Wiring and ground cable laying for Zirc–Észak-Litér line

Lot 3 covers wiring and ground cable laying works for the 132 kV Zirc–Észak-Litér transmission line. The scope includes a 21.2 km overhead section and a 1.1 km underground cable section, with specified conductor and optical cable types, plus post-completion operating and HIF permit procedures. The route crosses several Veszprém county settlements. The lot duration is 99 working days, excluding 15 December to 15 January.

WorksEU fundedElectronic submissionSME suitable

Ort

Zirc Észak-Litér közötti nyomvonal, Hungary

Dauer

99 DAY

Kategorie

Construction work

Zuschlagskriterien

Price

Frist

Expired Aug 10, 2026

Vergabedetails

Veröffentlichungsdatum
08 Jul 2026
Sprachen
Hungarian

Referenzmetadaten

Rechtsgrundlage
32014L0025

Referenz-IDs

Ausschreibungs-ID
475172-2026